Westmount subdivision

The Westmount subdivision is a 7.4-km section of track between the Montréal-Ouest and Lucien-L’Allier stations and an important point of convergence in the network: trains from the Vaudreuil-Hudson, Saint-Jérôme and Candiac lines must use it to reach the Lucien-L’Allier station. A total of 30,000 train users pass through this corridor every day!

 

Improving service and punctuality

The configuration of the train tracks and the condition of the railway signals have shown their limits. For example, when a single train breaks down or is simply delayed along the corridor, this produces a domino effect: delays accumulate and have significant repercussions on the three train lines. We had no choice but to intervene!

 

Developing the infrastructures

The railway infrastructure improvement work mainly focused on the following elements:

  • Extending track #1 (third track) over a distance of 4.8 km
  • Widening the Vendôme station platform to serve track #1
  • Installing links between tracks
  • Building a crash wall in the sector of the Côte-des-Neiges–Notre-Dame-de-Grâce borough

All of this work will let us improve the punctuality and flow of rail traffic, and also add departures!

 

We take your concerns to heart!

This work is necessary to improve or maintain our network, and we are doing everything in our power to minimize the inconvenience caused to our customers and to the residents who live near the tracks.

 

Work

Travaux de terrassement

Earthwork

Work completed in 2012

    • Extension of track #1 (third track to the south) all the way to the Montréal-Ouest station
      • Relocation of optical fibre: spring and summer 2012
      • Earthwork: spring and summer 2012

 

 Base de béton

Concrete bases at Prospect

Work completed in 2013

Portique de signalisation

Portique de signalisation

Mural artistique sur un mur d'impact

The mural, painted on the crash walls, keeps graffiti artists away from the track

Nouveaux portiques de signalisation

La pose des nouveaux The installation of new signal gantries began

Nouveaux portiques de signalisation

Installation of the new island platform at Vendôme station

  • The railway signalling system was replaced with a latest-generation system
  • Construction of concrete bases for the six signal gantries
  • Installation of signal support gantries and other signal elements
  • Construction of a crash wall south of the future track #1 (third railway track) at the level of the footbridge on Grand Boulevard (with the addition of the third track to the south, a protective wall had to be built to comply with the railway legislation in effect)

 

Work completed in 2014

  • End of construction work for a crash wall south of the future track #1 (third railway track) at the level of the footbridge on Grand Boulevard (with the addition of the third track to the south, a protective wall had to be built to comply with the railway legislation in effect)
  • Construction of concrete bases for the six signal gantries
  • Start of the installation of signal support gantries and other signal elements
  • Installation of a portion of interchange track between tracks to Loyola
  • Start of the extension of track #1 (third track to the south) over a distance of 4.8 km, from Vendôme station to Montréal-Ouest station (fall 2014 to fall 2015)
    • Construction of a portion of track #1 (third track) between Regent Avenue and Cavendish Boulevard

 

Work completed in 2015

Spring

  • Earthwork in preparation for the laying of track #1 (third track) (Vendôme section)

Spring to fall

  • Modernization of the railway signalling system:
    • Installation of signal support gantries and other signal elements
    • Commissioning of the signalling system between the Vendôme and Montréal-Ouest block sections
  • Vendôme train station:
    • Widening the Vendôme station platform to serve track #1 (third track)
    • Laying of interchange tracks
    • Laying of track #1 (third track)

Summer

  • Laying of track #1 (third track) over 4.8 km to Montréal-Ouest station (excluding Vendôme section)
  • Installation of interchange track between tracks (Concordia University – Loyola campus sector) and Vendôme
  • Maintenance work by CP (Montréal-Ouest station sector)
    • Repair of track at station platform level at Montréal-Ouest station
    • Repair of Westminster level crossing

Thanksgiving weekend

  • Realignment of tracks to the east of Elmhurst Street (Montréal-Ouest station area)
  • Details of work:
    • Dismantling of existing infrastructures: interchange tracks, switch, 600 feet of track
    • Installation of three track connection panels
    • Realignment, ballasting, surfacing and stabilization of three tracks
    • Checking and commissioning of signalling